Upper Heyford Sewage Treatment Works

Client:Xylem Water Solutions for Thames Water
Flow Rate:9l/s

Background

Thames Water were in the process of refurbishing the Sewage Treatment Works at Upper Heyford Sewage Treatment Works which was to be undertaken by Xylem Water Solutions. During the refurbishment they needed temporary treatment facilities to ensure discharge consents were maintained.

 

The Overall Objective

The works had a consent standard for 50% during the refurbishment and required a temporary replacement for primary settlement and biological treatment.

Solution

Siltbuster Process Solutions provided full support during the process and as a result installed a HB40R Clarifier as the primary tank, MBBR30 for biological treatment plus a D25 DAF for final solids preparation.

The plant was onsite for 3 months and it is estimated that using the temporary solution instead of tankering offsite reduced costs by 50 – 60%.

Back to top
An Ecoclear unit is just being loading destined for Sweden. A true masterpiece of innovation and engineering, the… https://t.co/gnbUPMjLKG
2:42 PM 2 Apr 2020 Join the conversation
Our engineering, workshop, stores, fleet services and yard teams are extremely busy preparing equipment for immedia… https://t.co/v7zCBClXZk
2:11 PM 2 Apr 2020 Join the conversation
#Siltbuster installation completed & fully operational on a wind farm construction site in Dunbar, Scotland. MT30,… https://t.co/cTfKeZcvRt
2:07 PM 2 Apr 2020 Join the conversation
Being a support and solutions provider to numerous Essential Services across the UK, our amazing team is providing… https://t.co/2zAS7SltPZ
11:42 AM 1 Apr 2020 Join the conversation
A #Siltbuster CM400 OWS is heading for a remediation site in Sweden with historical hydrocarbon pollution. This Oil… https://t.co/0Xfp5uEUnj
1:47 PM 26 Mar 2020 Join the conversation