Workdry International Group Websites

Tata Steel Dissolved Metals Removal

Client:Tata Steel
Location:Deeside
Flow Rate:120m³/hr

Background

The client was part-way through construction work required to accommodate a new production facility in one of its existing buildings. The method of construction required a series of well points to be installed around the periphery of sheet piles so as to lower the water table and prevent the base of the excavation from heaving.

Soon after dewatering commenced, the dissolved iron concentration in the groundwater started to increase rapidly, to a point where it could compromise compliance with the discharge consent limit. At that point Tata stopped the dewatering process and put the project on hold whilst a suitable method of removing the dissolved iron was sourced.

The Overall Objective

Tata required a solution that could be rapidly deployed and that could treat 120m³/hr of groundwater containing 70mg/l of dissolved iron 24 hrs per day without interruption for the full 10 week construction period, whist ensuring compliance with the 10mg/l Iron limit.

Solution

The process deployed on site involved a combination of pH adjustment and aeration to precipitate the dissolved iron and then to separate the precipitate from the water using DAF technology. Because of the large volume water to be treated, the solids recovered by the DAF plant were then dewatered using a mobile filter press mounted on an articulated lorry.

During the whole 10 week project duration some 180,000m3 of groundwater was treated and over 10 tonnes of dissolved iron was prevented from contaminating the River Dee.

Tata’s Senior Project Engineer Simon McCormick commented “without the expertise and swift response from Siltbuster, the project could have been delayed for several months with significant additional costs incurred whilst an alternative method of construction was developed and implemented.”

Back to top
Our first 1 day practical pollution awareness course will be at Cadbury World, Birmingham on the 27th March. Book y… https://t.co/xhiwfisNEd
1:30 PM 8 Feb 2019 Join the conversation
SPS are proud to be working with Alpheus Environmental to provide additional water treatment capacity to an industr… https://t.co/A8dLU5FNZt
8:29 AM 5 Feb 2019 Join the conversation
We will be presenting at the free Geotex Liverpool ground engineering seminar on the 20th Feb. Register now to find… https://t.co/GTUJcOPDC1
1:18 PM 1 Feb 2019 Join the conversation
Siltbuster will be exhibiting again at this year's Concrete Show, March 20-21 at the NEC. Come and chat to us on st… https://t.co/yrEWqByaN8
11:32 AM 28 Jan 2019 Join the conversation
Booking is open for our 2019 programme of Managing Water Pollution on Construction Sites training courses! Find ful… https://t.co/g0nZ8PQ5AA
10:19 AM 28 Jan 2019 Join the conversation