Northwich Waste Water Treatment Works

Client:United Utilities
Flow Rate:125m³/hr

Background

Northwich Waste Water Treatment Works had difficulty achieving their solids compliance of below 45mg/l and required a temporary solution to prevent non compliance’s in future. During periods of dry weather the site struggled with solids compliance which were averaging 40mg/l but could peak at 82mg/l.

The crude sewage was highly alkaline which added to the solids being slow settling in nature.

The Overall Objective

The overall objective was to reduce the Total Suspended Solids content however United Utilities also wanted to reduce the Phosphorus and Iron concentrations with chemical dosing, due to an upcoming Phosphorus limit being introduced.

Solution

SPS supplied and installed a D100 DAF with and integral sludge pump and walkways to ensure United Utilities were achieving their discharge consent.

 

Back to top
Great Night @MadeInWales Awards this evening. @Siltbuster Winners of the Manufacturing Innovation Award. https://t.co/UMuW9Ldy9D
9:47 PM 3 Oct 2019 Join the conversation
Blue skies today in Monmouth. Here's some of the fleet in the yard enjoying the nice weather. The kit is ready for… https://t.co/dgTZqDa3ew
10:16 AM 20 Sep 2019 Join the conversation
Richard. D. Coulton, talks to @Buildingtalk about the top causes of water pollution on construction sites, the impa… https://t.co/Oiyjmm75vY
10:23 AM 3 Sep 2019 Join the conversation
Siltbuster are helping Gothenburg construct a new metro while protecting the environment @SmartRailWorldhttps://t.co/BRjm2kr4dz
11:18 AM 25 Jul 2019 Join the conversation