Marlborough Waste Water Treatment Works

Client:Black & Veach
Flow Rate:140l/s

Background

Marlborough Waste Water Treatment Works provides treatment in the English County of Wiltshire and releases water in to the River Kennet. The treatment works needed to take their primary tanks offline for refurbishment work needed to maintain the level of treatment.

The Overall Objective

The site required a solution that would enable them to take the primary tanks offline for refurbishment and continue to treat the large flows required and protect the works from any risk of failing the suspended solids and BOD/Ammonia consent.

Solution

Siltbuster Process Solutions proposed a treatment system consisting of 4 HB40R units, auto de-sludge systems, interconnecting pipework and manifolds with easy access via 2 walkways.

Back to top
Siltbuster are helping Gothenburg construct a new metro while protecting the environment @SmartRailWorldhttps://t.co/BRjm2kr4dz
11:18 AM 25 Jul 2019 Join the conversation
If you're at #EWWMconference in Birmingham today or tomorrow, drop by our Siltbuster Process Solutions stand to dis… https://t.co/MKIdXPh7vp
10:34 AM 16 Jul 2019 Join the conversation
Looking forward to the award night on Thursday! https://t.co/X4gMQNyzOX
7:25 AM 10 Jul 2019 Join the conversation
SPS have a feature in Food Processing Magazine where Rich Matthews discusses how companies are using compact treatm… https://t.co/QveYldVlzV
8:31 AM 2 Jul 2019 Join the conversation
See this and more at outdoor stand DA1 https://t.co/GunKIXwcMe
8:57 AM 7 Jun 2019 Join the conversation