Llanfaglan Waste Water Treatment Works

Client:Welsh Water
Flow Rate:108m³/h

Background

Llanfaglan Waste Water Treatment Works serves the North West Wales Region. The works needed to take their final settlement tank offline for a period of over 5 weeks in order to carry out maintenance work.

The Overall Objective

During the time maintenance work the Settlement Tank would need to be drained and a suitable alternative would be required to take its place and enable the site to stay online and ensure they remained compliant with discharge consents.

The site required a solution able to cope with flows of over 100m³/h whilst also dealing with very slow settling solids.

Solution

Siltbuster Process Solutions proposed a treatment system that would enable Llanfaglan to remain online continue to achieve their consent limits. The system consisted of 4 HB50E Clarifiers, 4 sludge pumps with auto timers plus interconnecting pipework for the inlet, outlet and sludge, with 2 walkways for easy access.

Back to top
Gritbuster on the box! Filming for CBeebies "Do You Know?" took place yesterday at a large road sweeper depot in Te… https://t.co/c3ARSny7tE
8:28 AM 9 Apr 2019 Join the conversation
Whoever you are, wherever you are, water is your human right. 2.1 billion people live without safe water at home. T… https://t.co/ZdtHVcK9JK
9:53 AM 22 Mar 2019 Join the conversation
Siltbuster are in Stockholm to exhibit at 'Renare Mark' (Cleaner Ground) with our long time partner Clean Water Eng… https://t.co/lqtNKKu2Lu
2:28 PM 20 Mar 2019 Join the conversation
Equipment is only part of the Solution when it comes to complying with Environmental Legislation. Discover what els… https://t.co/Z628ffEeiO
8:58 AM 19 Mar 2019 Join the conversation
Siltbuster are supporting #RedNoseDay with a cake sale and competition at our Monmouth HQ to raise money to support… https://t.co/Nih1hUbsSR
10:01 AM 15 Mar 2019 Join the conversation