Llanfaglan Waste Water Treatment Works

Client:Welsh Water
Flow Rate:108m³/h

Background

Llanfaglan Waste Water Treatment Works serves the North West Wales Region. The works needed to take their final settlement tank offline for a period of over 5 weeks in order to carry out maintenance work.

The Overall Objective

During the time maintenance work the Settlement Tank would need to be drained and a suitable alternative would be required to take its place and enable the site to stay online and ensure they remained compliant with discharge consents.

The site required a solution able to cope with flows of over 100m³/h whilst also dealing with very slow settling solids.

Solution

Siltbuster Process Solutions proposed a treatment system that would enable Llanfaglan to remain online continue to achieve their consent limits. The system consisted of 4 HB50E Clarifiers, 4 sludge pumps with auto timers plus interconnecting pipework for the inlet, outlet and sludge, with 2 walkways for easy access.

Back to top
Our first 1 day practical pollution awareness course will be at Cadbury World, Birmingham on the 27th March. Book y… https://t.co/xhiwfisNEd
1:30 PM 8 Feb 2019 Join the conversation
SPS are proud to be working with Alpheus Environmental to provide additional water treatment capacity to an industr… https://t.co/A8dLU5FNZt
8:29 AM 5 Feb 2019 Join the conversation
We will be presenting at the free Geotex Liverpool ground engineering seminar on the 20th Feb. Register now to find… https://t.co/GTUJcOPDC1
1:18 PM 1 Feb 2019 Join the conversation
Siltbuster will be exhibiting again at this year's Concrete Show, March 20-21 at the NEC. Come and chat to us on st… https://t.co/yrEWqByaN8
11:32 AM 28 Jan 2019 Join the conversation
Booking is open for our 2019 programme of Managing Water Pollution on Construction Sites training courses! Find ful… https://t.co/g0nZ8PQ5AA
10:19 AM 28 Jan 2019 Join the conversation