Cuckfield Waste Water Treatment Works

Client:Southern Water
Flow Rate:43m³/h

Background

Cuckfield Waste Water Treatment Works serves the local area in West Sussex. Southern Water were upgrading the works to reduce the risk to the discharge permit.

The Overall Objective

The site had a small footprint available in an area with high bedrock and needed to reduce their costs.

Solution

SPS were approached to provide a cost effective solution that would upgrade the existing treatment works. As a result 2 HB50R Lamella Clarifiers providing a settlement of 100m³. SPS installed the units with walkways within a footprint of only 30m².

The system treated flows 43m³/hr and helped to reduce the flow through the existing systems.

Back to top
Yet another EcoClear unit, co-developed with our strategic partner Aquajet Systems AB in Sweden, is heading for the… https://t.co/gABq9cdezj
11:02 AM 7 Feb 2020 Join the conversation
It is great to see our HB Lamella Clarifiers ready for installation by PR Power as part of the treatment process of… https://t.co/CM6tzznaxE
9:24 AM 7 Feb 2020 Join the conversation
Enjoy the views of our modular treatment solution at Porlock WRC, to be used during the upgrade of the site’s exist… https://t.co/ky0aTR9qvG
9:12 AM 7 Feb 2020 Join the conversation
A further 4 of our industry leading HB50E's are on their way to Clean Water Engineering in Sweden. Destined for con… https://t.co/12ORCJPf7k
3:48 PM 29 Jan 2020 Join the conversation
We are very proud to confirm that our industry leading water treatment solutions and products, expertly deployed by… https://t.co/Uxv7vU430I
1:36 PM 23 Jan 2020 Join the conversation