Upper Heyford Sewage Treatment Works

Client:Xylem Water Solutions for Thames Water
Flow Rate:9l/s

Background

Thames Water were in the process of refurbishing the Sewage Treatment Works at Upper Heyford Sewage Treatment Works which was to be undertaken by Xylem Water Solutions. During the refurbishment they needed temporary treatment facilities to ensure discharge consents were maintained.

 

The Overall Objective

The works had a consent standard for 50% during the refurbishment and required a temporary replacement for primary settlement and biological treatment.

Solution

Siltbuster Process Solutions provided full support during the process and as a result installed a HB40R Clarifier as the primary tank, MBBR30 for biological treatment plus a D25 DAF for final solids preparation.

The plant was onsite for 3 months and it is estimated that using the temporary solution instead of tankering offsite reduced costs by 50 – 60%.

Back to top
We're at the #EWWM conference today and tomorrow. Drop by for a chat about DAF, MBBR and Lamella water treatment so… https://t.co/WRc15K09lJ
9:58 AM 17 Jul 2018 Join the conversation
A few places remaining on the Siltbuster 2-day Environmental Professionals CPD course in Reading 18/19 July. Book n… https://t.co/OqWZhuWCfb
9:26 AM 3 Jul 2018 Join the conversation
Another batch of HB50Es are ready and on their way to our partner Telstar in France to further support the surface… https://t.co/HBXJcNat1o
2:16 PM 28 Jun 2018 Join the conversation
Download your free copy of Siltbuster's white paper explaining the EA's Regulatory Position Statement – “Temporary… https://t.co/rKmmA0d1NS
10:41 AM 22 Jun 2018 Join the conversation
We’ve got new positions (Senior Process Design Engineer and Technical Sales Engineer – Municipal) on our website… https://t.co/gs1qEKjqZX
9:22 AM 15 Jun 2018 Join the conversation