Client:Kier Services

Background

Kier services are a tier two contractor working with South West Water and their H5O delivery partners to deliver its Amp 6 programme. At the Tregaseal Waste Water Treatment Works in Cornwall they have an activated sludge process, and the diffuser assemblies and mixers had been affected by a large build up of rag and grit in the aeration basin.

The Overall Objective

The aeration ditch was to be taken offline – so there was no other treatment on site. The process equipment needed to provide the quality specified by the Environment Agency.

SPS were contacted to provide a solution to supply, commission and decommission of a temporary primary treatment works to deal with the flow and reduce the suspended solids before discharging to sea.

Solution

SPS supplied and installed a Lamella DAF D100 to increase hydraulic capacity, and enhanced solids removal capabilities. Chemical was added to improve solids separation.

Back to top
SPS will be at next month's Food and Drink show in Coventry with Dave Gaskill speaking. Register to attend for free… https://t.co/RV0NNaHCxv
9:46 AM 17 Sep 2018 Join the conversation
Our 1 day Managing Water Pollution on Construction Sites CPD training course is coming to the Welsh capital on the… https://t.co/1I1q4iZyL7
1:06 PM 10 Sep 2018 Join the conversation
Siltbuster can help advise. For more information read our post: https://t.co/uF1rKwwCs7 https://t.co/GGR01lLw0T
11:19 AM 4 Sep 2018 Join the conversation
We're excited for this weekend's raft race on the beautiful river Wye. This year we're entering a joint team with o… https://t.co/mv4ti6tmr4
11:58 AM 31 Aug 2018 Join the conversation
What does the Environment Agency’s RPS mean for construction companies? Read our feature in Developer Update: https://t.co/OfBar5LX8r
12:24 PM 24 Aug 2018 Join the conversation