Llanfaglan Waste Water Treatment Works

Client:Welsh Water
Flow Rate:108m³/h

Background

Llanfaglan Waste Water Treatment Works serves the North West Wales Region. The works needed to take their final settlement tank offline for a period of over 5 weeks in order to carry out maintenance work.

The Overall Objective

During the time maintenance work the Settlement Tank would need to be drained and a suitable alternative would be required to take its place and enable the site to stay online and ensure they remained compliant with discharge consents.

The site required a solution able to cope with flows of over 100m³/h whilst also dealing with very slow settling solids.

Solution

Siltbuster Process Solutions proposed a treatment system that would enable Llanfaglan to remain online continue to achieve their consent limits. The system consisted of 4 HB50E Clarifiers, 4 sludge pumps with auto timers plus interconnecting pipework for the inlet, outlet and sludge, with 2 walkways for easy access.

Back to top
Some Siltbusters looking good in the sun! These two lorries are heading for a large infrastructure project in Somer… https://t.co/BmZzh1wz6g
1:36 PM 19 Apr 2018 Join the conversation
SPS and Suez cooperate to deliver clean water for Italian fertilizer manufacturer under highly variable conditions… https://t.co/WtqxqjrdAJ
3:52 PM 17 Apr 2018 Join the conversation
Glad to be part of the event and looking forward to some interesting conversations. https://t.co/OZFOOrExk0
12:02 PM 11 Apr 2018 Join the conversation
Great feedback from our recent win. https://t.co/zb7TtkObao https://t.co/0rhjSppOfZ
1:24 PM 27 Mar 2018 Join the conversation